Project guide
One schedule, several area types, one order.
Commercial projects do not fail on the fan choice. They fail on the gap between the schedule, the finish board and what actually arrives in the cartons.
A hotel lobby, a café, a guest floor and a back-of-house kitchen need different fans, and they usually need them from the same supplier on the same delivery. The way to keep that under control is a schedule: one row per area type, one decision per column, agreed before any price is requested.
This is the schedule format we work from when a buyer sends drawings. Build it first and the quotation stops being a guess; build it late and you will be changing finishes after the tooling is set.
1. Write the areas, not the rooms
Group the floor by area type — public-facing, work area, back-of-house, covered outdoor — and give each group a diameter and a model, then carry the count. A plan with forty room numbers is usually four or five area types wearing different labels, and collapsing them early is what keeps a project to two or three part numbers instead of twelve.
Note the ceiling construction next to each group while you are in the drawings. The public areas may be a suspended grid and the work area a concrete deck, and those two need different mounting decisions from the same supplier.
2. Fix light colour temperature by area, not by preference
Where the fan carries the room light, colour temperature becomes an interior decision with a consistency requirement: two areas visible from one another must not arrive in different whites. Some models in the catalogue offer a selectable three-CCT LED kit, which is useful precisely for this — the same part number can be set warm in the seating area and neutral over the counter.
Decide the value per area type and write it into the schedule. Retaining a spare quantity in the same configuration is cheaper than matching a colour temperature two years later.
3. Decide control before you order remotes
Most catalogue models ship with a hand remote, and on a commercial floor that means one remote per unit plus a spares allowance and a labelling job. Where the client wants switching from the wall or a single point of control, raise it at schedule stage: the control configuration is one of the items we open for custom orders, and it has to be settled before the electronics are specified for the destination market.
For any project that expects a building-management interface, say so explicitly and early. It is not a catalogue default and it is not something to discover at commissioning.
4. Match the finish to the joinery sample
Specify from a physical finish board against the joinery and ironmongery, not from a photograph on a screen. Black, brass-tone and wood-tone are the finishes we run as standard, and product colour is opened to custom orders when a project has a specified RAL — with the consequence that a custom colour becomes a new designation and a new minimum quantity.
For the iron-blade models, blade profile and edge finish read strongly at close range in a café or retail fit-out. Approve a sample before committing the floor.
5. Quote the schedule as one mixed order
Minimum order is two cartons on most models and ten pieces on the eight-blade large-diameter series, and mixed models can be combined in one order. That is what makes a five-area schedule commercially viable: you are not forced into a full container of each part number to satisfy a per-model minimum.
Send the schedule as a spreadsheet with the count column and we return a line-by-line FOB Zhongshan quotation in USD, with export packing included and freight and duties quoted separately against the destination.
Checklist
- One row per area type, with ceiling construction noted
- Diameter, model and unit count per row
- Colour temperature fixed per area, with spares in the same configuration
- Control method decided per area, including the spares and labelling load
- Finish approved from a physical board, not a screen
- Counts converted into one mixed order rather than per-model minimums
More buying guides
Enquiry
Send a model, a quantity and a destination.
That is enough for a real quotation. Catalog prices are a starting range, not a final offer.
Reply within one working day
Enquiries are answered by the export desk in Zhongshan, not an outsourced inbox.
Quoted on FOB terms
USD, export packing included, with the freight option that matches your destination.
Documents before you commit
Test reports, certificate files and packing dimensions are sent with the quotation.